The two-year Tier 2 extension
Sources checked November 25, 2026.
Written by Clean Buildings Filing, a private business that prepares Tier 2 filings for a fee. We are not the Department of Commerce.
A Tier 2 owner can ask the Department of Commerce for a two-year extension, to July 1, 2029, by applying in the Clean Buildings Portal between January 1, 2027 and January 1, 2028 and documenting one of five grounds in the rule. An extension gives more time without counting as compliance, and Commerce has not said what it does to the incentive.
Who can ask, and when
RCW 19.27A.210 lets the owner of a covered building apply to Commerce for an extension, and says requests "must be received by the department no sooner than six months prior to and up to six months after the applicable compliance date in order to be processed by the department." The Tier 2 compliance date is July 1, 2027, so the window runs from January 1, 2027 to January 1, 2028. Commerce's example timeline for a Tier 2 building gives the same closing date.
Commerce's extension guidance describes the extension as being for buildings "that are working towards compliance but cannot meet their respective compliance deadlines." The owner or an authorized representative applies. Commerce's guide to roles lists the building owner as the only required role for a Tier 2 extension application, so no qualified energy manager is needed to apply.
The five grounds
WAC 194-50-160 requires the application to meet at least one of five criteria and to include documents that support it. These are the rule's words.
"Beyond control. Building owner experiences conditions beyond their control, the effects of which could not have been avoided by exercising reasonable diligence, which substantially interfere with compliance efforts or schedule," including natural disasters declared by government officials and "Goods and services shortages causing delays."
"Change of ownership. Building owner purchases building in an arm's length transaction, with a date of purchase within 12 months prior to or on the exact compliance date."
"Financial restrictions. Building owner has financial restrictions requiring additional time to demonstrate full compliance. Financial hardship in accordance with Annex Y, Section Y4.1 (2)(g), affecting cash flow." The section it cites is the financial hardship list in the exemption rule, which our guide to exemptions sets out.
"New construction. Building owner has active or recent construction with a valid building/demolition permit limiting the ability to obtain 12 consecutive months of measured energy use prior to the building compliance date." The rule counts an addition, remodel or demolition that modifies at least 10 percent of the square footage and affects the conditions of compliance.
"EMP and O&M. Building owner complies with the requirements of the standard for benchmarking (Section 5.2 Building energy monitoring, and Section 7.2.1 Determining energy use intensity target (EUIt)) can receive an extension to comply with the EMP and O&M program requirements (Section 4.2 Energy management plan and operations and maintenance program)." In plain terms, an owner whose benchmarking and energy use intensity target are done can have two more years for the plan and the program. The target still has to be developed by a qualified energy manager.
How to apply
The application goes in through the Clean Buildings Portal. Commerce's Tier 2 page says it must include "documentation supporting the reason for the extension, the extension reporting tool (PDF)," and a showing that at least one of the criteria applies. Commerce's Tier 2 toolkit asks for "at least one acceptable supporting document."
The Extension Reporting Tool asks for the Commerce Building ID and the planned route to compliance, and puts three questions to the owner. "Why is an extension being requested for the building?" "What efforts have been taken towards compliance for this building so far?" "What is the plan for bringing the building into compliance?" We found no published review time for extension applications.
What an extension changes
The rule says a granted extension "is valid for two years beyond the covered building's compliance date." For Tier 2 that is July 1, 2029. When it runs out, the owner "must submit an application to the AHJ, for an exemption or to demonstrate compliance, or they will be subject to potential penalties." The AHJ is Commerce. The statute mentions renewing an extension, but Commerce's extension guidance marks renewal as open to Tier 1 buildings only.
In the guidance's words, "Extensions are not a compliance pathway; they provide building owners with additional time to pursue CBPS compliance."
On penalties, the rule says two things. An application for extension is one of the accepted answers to a notice of violation, and the potential penalties quoted above come into play when an extension has expired and nothing has been filed.
The incentive: Commerce has not said
None of the Commerce pages and documents we opened says what an extension does to the Tier 2 incentive. RCW 19.27A.220 keeps incentive applications open through June 1, 2030, while Commerce's incentive page says compliance and incentive applications must be submitted by July 1, 2027. Commerce's Tier 2 toolkit says the incentives are available only for the first compliance cycle, and the money is paid first come, first served.
An owner who wants both the extension and the incentive should put the question to Commerce in writing before relying on either date. Commerce's application guidance gives cbpsincentives@commerce.wa.gov for incentive questions.